-- part name: Keyboard Shortcuts: Task Info Window
----- HyperTalk script -----
on mouseUp
go card id 55102
end mouseUp
-- part contents for background part 31
----- text -----
Adding Actual Data
-- part contents for background part 32
----- text -----
In the Task Info Window
-- part contents for background part 6
----- text -----
Type the Actual Start date of that task, press Tab to move to the Actual Finish field, and type the finish date of the task, if applicable.
-- part contents for background part 27
----- text -----
3.
-- part contents for background part 7
----- text -----
If the task is complete, press Tab to move to the % Done field and type 100.
MacProject II indicates that the task is complete by filling its box with a pattern of dots in the Schedule Chart. You can also mark a task complete by selecting the task in the Schedule Chart and choosing Mark Complete from the Task menu.
If the task is not complete, you can type a number in the % Done field to indicate the portion of the work that is finished.